Green Man Lane

Current status and next steps

Current status

Phase 1 completed in April 2014 and contains 162 new homes. All social rent homes have been tenanted by estate tenants.

Phase 2A, a small phase containing 10 flats and four houses, was completed in July 2012 and tenanted by estate tenants.

Phase 2B, containing 188 new homes completed in August 2017 and tenanted by estate tenants

Phase 3 is currently under construction and is due for completion in March 2021 providing 180 mixed tenure homes.

Phase 4, the last phase, is currently being decanted in preparation to provide vacant possession of the site for demolition in June 2021.

The scheme as a whole will provide 714 new homes (338 social rent, 63 shared ownership and 313 private sale)

St Johns School

The Green Man Lane regeneration scheme expanded to include increasing the capacity of the existing St John's Primary School, a MUGA and build 92 new homes.

Phase 4A, a wing of the Tintern Court complex, was emptied and is now demolished along with the Community Centre. This area along with part of the existing St Johns Primary School playground was used to build the new enlarged school which opened in October 2017. The temporary Community Centre has been erected in another part of the estate.

 The completed work provided:

  • 630 place 3 form entry (3FE) primary school with 100 place (50 place per session) nursery.
  • re-provision of Jubilee Hall children’s centre
  • 55 new homes for sale
  • 22 additional parking spaces

Next steps

Phase 3 is currently under construction. A planning application for Phase 4 is to be submitted late 2019