Current status and next steps
Current status
Phase 1 completed in April 2014, construction of 162 new homes. All social rent homes have been tenanted by residents.
Phase 2A, completed in 2012, building of 10 flats and four houses, tenanted by residents.
Phase 2B, completed in August 2017, building of 188 new homes and tenanted by residents.
Phase 3, completed in August 2021, building of 143 new homes of which 60 are social rent, 14 shared ownership and 69 private sale homes.
Phase 4, the last phase, is almost empty and planning is being reviewed by the GLA to provide a further 396 units on this phase.
St Johns School - the Green Man Lane regeneration scheme expanded to include increasing the capacity of the existing St John's Primary School, a MUGA and 92 new homes.
Next steps
A planning application for Phase 4 is being reviewed by the GLA and works are expected to start in 2025 to build 396 new homes.