18 November 2024: Ealing Council submitted the draft New Local Plan for examination. More information on the appointment of the independent inspectors and the details of the examination process will be published, when known. This may take up to 3 weeks.

16 December 2024: (Ref: EX1) A cover letter from Ealing Council was sent to PINS

18 December 2024: A letter confirming the appointment of the Inspectors who will conduct the examination has been received.

20 December 2024: (Ref: EX2) A letter containing a series of initial questions from the Inspectors has been received. No response other than from the council is invited at this stage.

10 January 2025: (Ref: EX3) Council responds to the initial questions from the Inspectors. The Inspectors are not inviting any comment on the council's response

13 January 2025: (Ref: EX4) Council responds to Initial Question 4

17 January 2025: (Ref: EX5) Council responds to Initial Question 17

22 January 2025: (Ref: EX6) Letter is sent to Representors to advise of Inspector Appointments

23 January 2025: (Ref: EX7) Letter to council - Initial Questions follow up

23 January 2025: (Ref: EX8) Council responds to Initial Question 18

29 January 2025: (Ref: EX9) Council responds to Initial Questions 3 and 13

28 February 2025: (Ref: EX10) Council responds to Initial Question 4, 9 and 11

28 February 2025: (Ref: EX11) Council responds to Initial Questions 6 and 7

3 March 2025: (Ref: EX12) Council responds to Initial Question 7

7 March 2025: (Ref: EX13) Council responds to Initial Question 6

8 April 2025: (Ref: EX14) Indicative running order for hearing sessions

8 April 2025: (Ref: EX15) Inspectors guidance notes

8 April 2025: (Ref: EX16) Matters, Issues and Questions